"AS Group Investment" company performed the following works in the construction of the 1st phase of the Alat Free Economic Zone:
- Stormwater - 4 629 m
- Micro tunnel - 117 m
- Foulwater - 2570 m
- Potable water line - 7 743 m
- Technical water line - 2,099 m
- Gas line - 2610 m
- Irrigation water line - 29 129 m
- Underground passage - 1 unit
- Telecom - 84 163 m
- Area lighting - 21 928 m
- MV medium voltage line - 36208 m
- LV low voltage line - 31 041 m
- Safety line -19 006 m
- Roads - 4 300 m
- Fence - 3 241 m
- Customs checkpoint - 1 unit